Showing posts with label Gas Transmission. Show all posts
Showing posts with label Gas Transmission. Show all posts

Thursday, December 17, 2009

A study on Activity of Titas Gas Transmission & Distribution Company ltd. (TGTDCL), Bangladesh( Part-4)

2.5.5 Operation [10].
Inspections of operational works are:
 Co-ordination of pigging programs
 Cathodic protection readings
 Foreign crossing inspections
 Daily reading as required
 Co-ordinate R. O. W. surveillance

2.5.6 Maintenance and repair [10].
 Pump and compressor preventive maintenance and repair
 Pipeline repairs
 Valve maintenance and repair

2.5.7 Inspect the pipeline integrity programs 

Pipeline integrity programs are very important part of both pipeline operation and maintenance procedures. There are several functions that are required to form a complete pipeline integrity program, such as:
 Schedule pressure testing programs
 Annual river crossing profiles
 Pipeline coating assessment programs
 Depth of cover surveys
 Internal inspection surveys [10].

2.5.8 Inspection the Preparation for Welding

Safety regulations require the welding operation be protected from weather condition that would impair the quality of the welding. Before beginning the welding, welding surface must be clean and free of any material that may be detrimental to the welding. Also, pipe sections must be properly aligned for depositing the root bead. Specifications require that carbon steel with carbon content in excess of 0.32% must be preheated for welding. In some cases; steel with lower carbon contents must also be preheated. When steels with different preheated temperatures are being welded, the higher preheat temperatures must be used to weld the seams. Preheat temperature must be monitored to ensure the proper temperature and maintain that temperature during welding.             

Qualified trained welders must be employed for welding operation. TGTDCL has it’s own welder grades specified as Titas grade-A, B, C.  For high pressure pipeline a welding procedure specification (WPS) is established and suggest to follows these procedure strictly. Welding conducted as per the welding procedure and must be tested to ensure the WPS requirements fulfilment. Welded joints are inspected visually, mechanically and by using non-destructive test (NDT) methods. Mechanical test includes tensile test, nick break test, macro tech test, etc. Test results are to be documented and record the procedure of welding operation [1-2].

2.6 Inspection and Testing

Pipeline welds must be inspected visually to ensure the performance in accordance with the welding procedure and the welds are acceptable under the appropriate specifications. In the United States, to comply with provisions of 49 Code of federal regulation (CFR), non-destructive testing is also required on welds made on a pipeline that will be operated at a pressure that results in a hoop stress of 20% or more of the specified minimum yield strength (SMYS). There are two exceptions to this non-destructive testing requirement. Non-destructive testing is not required even though hoop stress will exceed 20% of SMYS if
·         the pipeline has a nominal diameter of less than 6 in.
·         the hoop stress will be less than 40% of the SMYS and the number of welds is so small as to make such testing impractical.
Non-destructive testing must be performed according to written procedures by specially trained personnel.

Radiography (X-ray) is the most widely used method for testing pipeline welds in non-destructive method. In radiography, a picture is made on a sensitized film by exposing the film to X-ray. Defects in the weld, such as cracks, porosity, or slag inclusions, appear as spots or lines on the developed film.

A study on Activity of Titas Gas Transmission & Distribution Company ltd. (TGTDCL), Bangladesh( Part-3)

2.5 Standard Inspection Methods:

2.5.1 Material procurement inspection
2.5.2 Visual inspection
2.5.3 Design inspection
2.5.4 Construction inspection
2.5.5 Operation
2.5.6 Maintenance and repair
2.5.7 Inspect the pipeline integrity programs
2.5.8 Inspection the Preparation for welding

2.5.1 Material procurement inspection
During pipeline construction materials are inspected visually and mechanically for their physical, dimensional defects and design accuracy. Materials are pre-qualified / inspected as per international standard during procurement [1].
The most common standards are:
 American Petroleum Institute ( API )
 American National Standard Institute ( ANSI )
 American Society of Mechanical Engineers ( ASME )

2.5.2 Visual inspection
Visual inspections are important in welding jobs for construction of pipelines. Cracks, incomplete penetration, burn-through, undercut, unequal leg length, and other imperfections in the test welds shall be assessed in accordance with the applicable requirements. Undercuts adjacent to the final test weld bead on the outside of the pipe shall not exceed 1mm in depth. The test welds shall have a neat appearance. Imperfections detected by visual inspections must be into consideration and take corrective measures.

2.5.3 Design inspection
The requirements for design inspection of pipeline construction project are:
 Fluid flow capacity
 Design pressure for each segment of pipeline system

°                       External pressures and loadings
°                       Ambient influence
°                       Temperature
°                       Location of Class
 
2.5.4    Construction inspection
Inspection of pipeline construction based on:
°                       Pre-construction activities
°                       Construction activities
°                       Post-construction activities

Pre-construction activities
Inspections of pre-construction activities of pipeline are as follows:
°                     Route selection
°                     Legal surveying and land acquisition
°                     Pipe hauling
°                     Equipments and vehicles

Construction activities:
Inspection of construction activities is very important for pipeline operation and integrity. When any pipe manufacturing defects are detected during installation inspection, the defective portion of pipe shall be repaired by the applicable pipe manufacturing standard or specification or cut out as a cylinder or where necessary replaced with another pipe that meets the design requirements. Inspection shall be performed by the experienced personnel. Inspection for piping defects shall be indentified immediately prior to the application of any field coating and during lowering in and backfilling operations. Pipe and component shall be inspected for defects. Such inspection shall include but not necessarily be limited to inspection for flattening, ovality, straightness, pits slivers, cracks, gouges, dents, defective weld seams, and defective field welds. Bends shall be inspected for conformance with the free from buckling, cracks, and other evidence of mechanical damage. Where the pipe is field coated, inspection shall be carried out to determine that the cleaning/coating machine is not creating defects in the pipe. Coating shall be inspected immediately before, during and after pipe installation. Faults in the coating shall be repaired and re-inspected. Plant-applied coatings shall be inspected immediately after field-bending to confirm that the integrity of the coating has been maintained. Where applicable, each pipe shall be visually inspected prior to welding for defects in its lining. Inspection of field and shop welds is in accordance with the applicable requirements of clause 7 [9]. Inspection of pipe portion repaired, replaced, and altered shall be made before it is backfilled. Where necessary and as appropriate, non-destructive inspection of piping shall be performed using one or more of the following methods:
(a)        Radiographic inspection of welds in accordance with the applicable requirements of clause 7.
(b)        Ultrasonic inspection of welds in accordance with the applicable requirements of clause 7.
(c)        Ultrasonic inspection of pipe
(d)       Electrical inspection of protective coating
(e)        Inspection using internal inspection devices and
Other methods are below:
°                     Stringing pipe
°                     Welding
°                     Coating
°                     Ditching
°                     Crossing
°                     Lower-in
°                     Backfilling
°                     Compression and pump station
°                     Pressure testing
°                     Clean-up and restoration    [10].

Post-construction activities
After the pressure test has been completed, it is then necessary to displace the test median from the pipeline and purge the system with sweet natural gas or an inert gas such as nitrogen to make the system ready for operation.


Seismic Energy Dissipation Devices

Seismic Energy Dissipation Devices